Project scheduler: critical path (CPM), float, PERT chance of finishing on time and a Gantt chart

List your tasks, durations and predecessors (finish-to-start, start-to-start, finish-to-finish, with lags) and get the critical path, earliest and latest dates, float, a Gantt chart, and with three-point estimates the PERT chance of finishing by a date, checked by simulation. Runs in your browser.

Keep it one tap away for everyday use.

Bookmark Project scheduling: CPM, PERT and Gantt?

Press Ctrl + D now. Your browser opens its own bookmark box, where you choose the name and folder.

  1. Tasks
  2. Links
  3. Critical
  4. Gantt
Nothing is uploadedWorks offline once open

Tasks

Predecessors: IDs separated by spaces, such as A B. Plain IDs mean finish-to-start. Add a lag with A+2 or A-1, and other link types with A SS, B FF+1 or C SF.

What it does

Every project has a chain of tasks that sets its length: the critical path. Delay any task on it and the whole project slips; tasks off it have float, time they can slip without harm. This tool works it out from a simple table of tasks:

  • a forward pass (earliest start and finish) and a backward pass (latest start and finish);
  • total float and free float for every task, and the critical path;
  • links of all four kinds, finish-to-start, start-to-start, finish-to-finish and start-to-finish, each with a lag (or a lead, a negative lag);
  • a Gantt chart, with optional calendar dates that skip weekends;
  • with three-point estimates, PERT: the expected duration, its standard deviation and the chance of finishing by a date, plus a Monte Carlo simulation that checks it.

How to use it

  1. Type or paste one row per task, or open a CSV or Excel file. A header row names the columns: ID, Task, Duration and Predecessors. For PERT, use Optimistic, Most likely and Pessimistic instead of Duration.
  2. Write predecessors as IDs with spaces between them: B C. A+2 waits 2 days after A finishes; A SS starts when A starts; A FF+1 finishes at least 1 day after A finishes; A SF finishes after A starts.
  3. Choose the time unit, and a start date if you want calendar dates.
  4. For PERT, type the time you must finish within.

Worked example

The first example is a small building project with three-point times. Each task’s PERT duration is (o + 4m + p) / 6; for “Draw the plans” (4, 6, 10 days) that is 6.333 days, with a standard deviation of (10 − 4) / 6 = 1 day. The schedule takes 30.5 days, along the critical path A → C → E → G → H → I. “Survey the site” (B) and “Prepare the site” (F) have 4.833 days of float, and “Order materials” (D) 3.833.

The variances along the critical path add up to 5.75, a standard deviation of 2.398 days. The chance of finishing within 32 days is therefore Φ((32 − 30.5) / 2.398) = 73.4 %, and you can be 90 % sure of finishing within 33.57 days. The simulation of 5,000 projects gives 73.5 % and 33.81 days: a little later at the 90 % mark, as simulation usually is, because near-critical paths sometimes take over.

The second example uses single durations with a start-to-start lag (E starts 2 days after C starts) and a finish-to-finish lag (H finishes at least 1 day after G); the project then takes 22 days.

Things to know

  • Tasks are scheduled as early as possible, from day 0, with unlimited resources. Resource levelling is not done.
  • With a start date and working days only, day 0 is the first working day on or after the start date; finish dates are the last working day of each task.
  • Up to 2,000 tasks. The Gantt chart shows the first 150 by start.

Frequently asked questions

What if my predecessors form a loop? The tool names the loop, such as B → D → B, so you can remove a link.

Is my plan uploaded? No. Everything is worked out in your browser and nothing is stored.

Where the numbers come from

  • Methods: the critical path method, PERT three-point estimates and the beta-PERT distribution, as in project management and operations research textbooks.
  • Checked against a longest-path calculation in Python (networkx Bellman-Ford on the start and finish events) for 1,200 random projects, half with SS, FF and SF links and lags, and the PERT figures against SciPy's normal distribution and a NumPy beta-PERT simulation.
  • The example project is made up.

Standard scientific values, such as constants, atomic weights and melting points, are facts found in every textbook; we name where ours were checked. If you are an author or publisher and want a value, a credit or a table changed or removed, tell us and we will act quickly.

Last updated 2026-11-09.

Related tools

Publication plot maker #27 Paste columns or open a CSV or Excel file and get a clean scientific figure with error bars, sized for a journal column. Download vector SVG or PDF, or PNG at 300 or 600 dpi. Your data stays in your browser. Linear and integer programming solver #582 Type a linear or integer program as plain text (maximize or minimize, constraints, bounds, whole-number and yes/no variables) and get the optimal solution, shadow prices, reduced costs, the simplex tableaux step by step, and a picture for two variables. Runs in your browser. Queueing calculator #584 Average waits, queue lengths, utilisation and the chance of waiting for the standard queue models, how many servers or agents you need for a target wait, and a discrete-event simulation that checks the formulas. Runs in your browser. Transportation and assignment problem solver #583 Solve a transportation problem from a starting plan (northwest corner, least cost or Vogel's approximation) to the optimum with the MODI method, showing every step, the u and v potentials and dummy rows for unbalanced problems. Or solve an assignment problem with the Hungarian method, minimising cost or maximising profit. Checked against scipy. Vehicle routing for small instances #586 Plan delivery routes from one depot: give the customers as map coordinates or a distance table, their demands, the vehicle capacity and the number of vehicles. Clarke-Wright savings with 2-opt and or-opt improvement, the exact shortest plan for up to 12 customers, a route map and a stop-by-stop table. Checked against brute force and an integer program. 1D Schrödinger solver #923 Choose a textbook potential, type a formula or draw your own, and get the lowest energy levels and wavefunctions of the one-dimensional Schrödinger equation by the matrix (finite-difference) method, with the exact levels alongside for the box, harmonic oscillator, finite well, Morse, linear and Pöschl–Teller potentials.